Permits & inspections

The job isn't finished until it passes.

Installing the equipment is the first half. The permit and the inspection are the second half — here's how that part works, and what we need from you.

A newly installed condenser anchored to its pad, ready for final inspection.
The sequence

What happens, in order.

01 · We pull the permit

Before the work starts. We file it under our license, with the equipment make and model on the application.

02 · We install

Equipment set, anchored, connected and started up. You have cooling the same day in most cases.

03 · The city inspects

Days or weeks later, a city or county inspector comes out to verify the work. That visit is what closes the permit.

The part people don't expect

The inspector doesn't give you a time.

This surprises almost every homeowner, so we say it early. Inspections in Cape Coral are requested through the city's online system the night before — by 9:00 PM — and the tickets are handed out to inspectors around 7:00 AM the next morning.

No appointment window is issued. The inspector arrives sometime during the working day. Once the ticket is assigned we can see who has it and call for an estimated time, but it stays an estimate.

Because of that, plan on someone being home and able to open the house between 8:00 AM and 1:00 PM on the inspection day. That's the window that covers most visits.

What we need from you.

  • Someone at the property, or a way in we've agreed on beforehand
  • Clear access to the air handler and the outdoor unit
  • Pets secured
  • Gate or community codes, if there are any
  • A phone number the inspector or we can reach on the day

If nobody can be there, tell us in advance — there are usually options, but they have to be arranged before the inspection is scheduled.

Questions about your inspection?

239-703-6006

Real work. Real results.

Good to know

A few things worth understanding.

A missed inspection costs a day, not a job

If nobody is home, the inspector leaves a notice and we reschedule. It delays the permit closing; it does not undo the installation.

The permit has a clock on it

In Lee County a permit expires if it hasn't passed an inspection within 180 days of being issued. We don't let one sit.

Some jobs get two inspections

A full system, air handler, heat pump or mini-split typically takes a rough inspection and then a final. A condenser-only change-out usually takes just the final.

Keep the paperwork

A closed permit is what proves the work was done to code. It matters when you sell the house, and it matters for the manufacturer's warranty.

A finished air handler installation with insulated line set and clean drain routing.
Who to contact

If you need to reach the city yourself.

Inside Cape Coral city limits: the City of Cape Coral Building Division handles permits and inspections. Their inspection help line is (239) 573-3173, open 7:30 AM to 2:00 PM, Monday through Friday.

Unincorporated Lee County: Lee County Development Services handles it instead. Which one applies depends on your address, not your mailing city.

You shouldn't need to call either of them — that's our job. But if you want to check the status of a permit on your own property, you can.